The Hon. Nalin Bandara Jayamaha

Samagi Jana Balawegaya· Kurunegala· 9 January 2025 ·Oral question: Oral Questions

InfrastructureEnvironment
AI summary generated by gpt-5.5

Asked for an update on the 100 MW Siyambalanduwa solar project, noting that although the award has been made, land clearance and inter-agency support remain pending. He questioned whether the Government is expediting the project and ensuring support from the CEB and relevant agencies so construction can begin as planned.

Verbatim record (translated)

Machine-translated from Sinhala / Tamil / English

¶ 01 Thank you. Regarding the 100 MW solar project in Siyambalanduwa, the award has been made, but land clearance is pending. Construction was due to start around January/February. Lack of support from the CEB and other agencies seems to be delaying it. Are you expediting and providing necessary support? What is the current status?

Provenance

Source
Hansard, Thursday, 9 January 2025 ·No. 1738229262040729 ·English daily/uncorrected Hansard
Page · column
not yet extracted — page/column anchors are not in the current dataset; the source PDF is the citable location.
Permalink
/lk/speeches/23623

Cite as: The Hon. Nalin Bandara Jayamaha. 10th Parliament, Parliament of Sri Lanka. Hansard, 9 January 2025. No. 1738229262040729. Politick, https://staging.politick.io/lk/speeches/23623