The Hon. (Prof.) A.H.M.H. Abayarathna - Minister of Public Administration, Provincial Councils and Local Government
The Minister acknowledged remaining gaps in the Greater Colombo wastewater projects and outlined the status of ADB-funded components, noting that several sewer rehabilitation, supply, and consultancy contracts have been completed while some pumping station, Kirulapone, and other works remain incomplete. He stated that further allocations are required and that the Government aims to complete outstanding works under the two projects by 31 December 2027. He also said foundational measures are underway to improve solid waste management operations and introduce new interventions.
Verbatim record (translated)
Machine-translated from Sinhala / Tamil / English¶ 01 The Hon. Member is correct regarding the scale and the remaining gaps.
¶ 02 The Greater Colombo Wastewater Management Project commenced in 2010 (loan agreement signed on 18 December 2009). ADB financing closed on 30 June 2023. As at 30.06.2023:
¶ 03 - Four main civil works contracts: • Rehabilitation of sewer networks in Modara North and Wellawatta South – completed. • Rehabilitation of 10 km of sewer lines and condition assessment of 125 km in CMC area – completed. • Upgrading of the gravity sewer network in Wanathamulla – completed. • Design, construction and rehabilitation of wastewater pumping stations within CMC limits – partially completed.
¶ 04 - Two supply contracts (e.g., mobile jetting and vacuum trucks, O&M equipment) – completed.
¶ 05 - Two consultancy contracts (design, supervision and project management) – completed.
¶ 06 The second component, the Greater Colombo Water and Wastewater Management Improvement Investment Program (loan agreements signed in 2014; implementation began in 2016; financing closed on 24 October 2022):
¶ 07 - Three main civil works: • Geotechnical investigations; 24 km of open-cut, trenchless and micro-tunneling works – completed. • Kirulapone sewer system and pumping station construction/rehabilitation – partially completed. • Wellawatta wastewater treatment facility contract – terminated by mutual understanding.
¶ 08 - One consultancy package – completed.
¶ 09 Some sections in both projects remain incomplete; therefore, further allocations are still required. Our target is to complete the outstanding works under these two projects by 31.12.2027.
¶ 10 Regarding solid waste, foundational steps are underway to address the issues highlighted, including enhanced operations and new interventions for waste management.
Provenance
- Source
- Hansard, Saturday, 8 November 2025 ·No. 22727 ·English daily/uncorrected Hansard
- Page · column
- not yet extracted — page/column anchors are not in the current dataset; the source PDF is the citable location.
- Permalink
/lk/speeches/6431
Cite as: The Hon. (Prof.) A.H.M.H. Abayarathna - Minister of Public Administration, Provincial Councils and Local Government. 10th Parliament, Parliament of Sri Lanka. Hansard, 8 November 2025. No. 22727. Politick, https://staging.politick.io/lk/speeches/6431