The response to Question No. 7 stated that Stage 1 of the East Terminal project at Colombo Port began in March 2013 and Stage 2 in April 2021. It further stated that a new road layout was approved on 22 January 2025 with the consent of Engineering and Operations division representatives, and that no related issue requiring further action had arisen.
Verbatim record (translated)
Machine-translated from Sinhala / Tamil / English¶ 01 Question No. 7 – 648/2025 – Construction of East Terminal of Colombo Port: New Road Plan.
¶ 02 Answer tabled:
¶ 03 (a) (i) Stage 1 – March 2013; Stage 2 – April 2021.
¶ 04 (ii) A new layout was approved on 2025.01.22 with the consent of representatives from Engineering and Operations divisions.
¶ 05 (iii) No.
¶ 06 (iv) Not applicable.
¶ 07 (b) Does not arise.
Provenance
- Source
- Hansard, Wednesday, 21 May 2025 ·No. 1749121318003248 ·English daily/uncorrected Hansard
- Page · column
- not yet extracted — page/column anchors are not in the current dataset; the source PDF is the citable location.
- Permalink
/lk/speeches/8087
Cite as: The Hon. Bimal Rathnayake. 10th Parliament, Parliament of Sri Lanka. Hansard, 21 May 2025. No. 1749121318003248. Politick, https://staging.politick.io/lk/speeches/8087