The Hon. Anura Karunathilaka — Minister of Urban Development, Construction and Housing

9 July 2025 ·Oral question: Oral Question: Ragama–Peralanda Tank Development (Q.6511/2025)

InfrastructureLand & Housing
AI summary generated by gpt-5.5

The Minister replied to a question on the Ragama–Peralanda project, stating that it was initiated on 12 October 2020 to manage flash floods, protect wetlands, prevent unauthorized filling and dumping, improve recreation facilities, and support local economic activity. He said the UDA estimated the project at Rs. 233 million, with about Rs. 199.86 million spent on completed Phases I and II, including desilting, walkways, slope protection, bridges, drainage, and lighting. For Phase III, Rs. 7 million has been allocated this year from the Budget and Provincial Council Fund, and after completion the project’s operation and maintenance will be handed over to the Ja-Ela Pradeshiya Sabha.

Verbatim record (translated)

Machine-translated from Sinhala / Tamil / English

¶ 01 Hon. Speaker, the answers are:

¶ 02 (a) (i) Yes. (ii) 2020-10-12. (iii) Objectives: - Control and management of flash floods in the Ragama–Peralanda area. - Protect environmental value as a wetland system and open space. - Enhance biodiversity. - Control unauthorized constructions and filling. - Prevent dumping of garbage and demolished debris into the tank and adjoining wetlands. - Improve public mental and physical health in densely populated Ragama by creating wellness walkways. - Create a pleasant environment with open seating, children’s parks, and tree planting for recreation. - Promote local economic development through eateries and small shops.

¶ 03 (iv) Estimated by UDA at LKR 233 million; expenditure to date LKR 199,863,870.30 (Phases I & II). (v) The project comprised three phases. Phases I and II have been completed, including desilting, a perimeter walking path, slope protection with gabions, handrails, two bridges/culverts, drainage works, and lighting to enable public use. (vi) For Phase III—particularly perimeter protection bunds and bridge embankments—LKR 5 million has been allocated in this year’s Budget, and the Provincial Council Fund has allocated LKR 2 million. Thus, LKR 7 million is allocated this year to complete Phase III. Upon completion, operation and maintenance will be handed over to the Ja-Ela Pradeshiya Sabha; they have been informed to take over.

¶ 04 (b) Does not arise.

Provenance

Source
Hansard, Wednesday, 9 July 2025 ·No. 1752660241032216 ·English daily/uncorrected Hansard
Page · column
not yet extracted — page/column anchors are not in the current dataset; the source PDF is the citable location.
Permalink
/lk/speeches/9206

Cite as: The Hon. Anura Karunathilaka — Minister of Urban Development, Construction and Housing. 10th Parliament, Parliament of Sri Lanka. Hansard, 9 July 2025. No. 1752660241032216. Politick, https://staging.politick.io/lk/speeches/9206